Wellington MBTA Yard Expanding In Medford
Renovations and upgrades are expected to take three years to complete.
BTA
✔
@MBTA
We then began adding 6 new tracks to the yard. This is to increase storage capacity—we need a place to house the current fleet of 120 cars *and* the new fleet of 152 cars, before the old ones are retired.
This is in progress and is expected to be complete by the end of 2018. pic.twitter.com/4VrZSGkGu0
This is in progress and is expected to be complete by the end of 2018. pic.twitter.com/4VrZSGkGu0